Road improvement scheme - including sections of Sandyford, Enniskerry and Hillcrest Roads at Lamb's Cross
Status: Construction
Murphy International Ltd awarded the construction contract for the Blackglen Road Improvement Scheme in August 2021.
Construction started late September 2021
Works at junction of Grange Road/Harold’s Grange Road/Kellystown Road/College Road Traffic Lights nearing competition.
Works on Blackglen Road are in progress with rock removal, boundary walls and retaining walls and regraded driveways.
Works at Lamb’s Cross and on Sandyford Road/Enniskerry Road have commenced. The current project (Blackglen Road Improvement Scheme) does not include improvement works to the Harold's Grange Road. This road improvement scheme is expected to be completed Q4 2023.