Project Updates
Round 1 - Bundle 1
Friday, 17th July 2026:

1. Works elements completed / ongoing:
Convent Road
- All major works are complete, with landscaping works to take place during planting season.
- Snagging will be taking place in the coming weeks.
- Road is fully open to traffic with no disruptions.
Brookfield Terrace
- Work on this section is substantially complete, with surfacing and snagging outstanding.
2. Works lookahead:
Convent Road
- Snagging
Brookfield Terrace
- Snagging
- Surfacing
3. Early warning items:
- Continue with snagging.
- Localised minimum delays may occur during certain construction phases, but disruption is expected to remain minimal.
4. Other:
- Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news.
Friday, 3rd July 2026:

1. Works elements completed / ongoing:
Convent Road
- Tree pits work civils on Convent Road are complete, with snagging outstanding.
- Surfacing works on Convent Road are complete.
- All major works at this location are complete, with line marking still outstanding.
Pedestrian access to the school remains fully maintained.
Brookfield Terrace
- Works on this section are substantially complete, with surfacing and snagging outstanding.
2. Works lookahead:
Convent Road
- Housekeeping and snagging
- Line marking
Brookfield Terrace
- Housekeeping and snagging
- Surfacing
3. Early warning items:
- Continue with snagging and line marking.
- Localised delays may occur during certain construction phases, but disruption is expected to remain minimal.
4. Other:
- Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news.
Friday, 19th June 2026:

1. Works elements completed / ongoing:
Convent Road
- Tree pits work civils on Convent Road are complete, with snagging outstanding.
- Works on Avoca PI on footpath upgrade and raised crossing are ongoing
- Pedestrian access to the school remains fully maintained.
Brookfield Terrace
- Works on this section are substantially complete with snagging outstanding.
2. Works lookahead:
Convent Road
- Finish out additional works on Avoca
- Housekeeping and snagging
- Surfacing
- Line marking
Brookfield Terrace
- Housekeeping and snagging
3. Early warning items:
- A temporary Road closure of Convent Road, Blackrock is proposed from Monday, 29th June 2026 to Friday, 3rd July 2026
- Continue with Avoca PI additional works as planned.
- Localised delays may occur during certain construction phases, but disruption is expected to remain minimal.
4. Other:
- Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news.
Friday, 05th June 2026:

1. Works elements completed / ongoing:
Convent Road
• Tree pit work excavation and preparations are ongoing.
• Pedestrian access to the school remains fully maintained.
Brookfield Terrace
• A Hippo gully has been installed, and the chamber cover has been replaced.
• Tactile paving and the footpath have been installed.
• Drainage works and footpath upgrade works will continue as planned
2. Works lookahead:
Convent Road
• Continue with tree pit works.
• Line marking
• Housekeeping and snagging
Brookfield Terrace
• Housekeeping and snagging
3. Early warning items:
Brookfield Terrace
• Tree pit works to be continued as planned.
• Localised delays may occur during certain construction phases, but disruption is expected to remain minimal.
4. Other:
• The next update is on Friday, 19 June 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 22nd May 2026:
1. Works elements completed / ongoing:
Convent Road
• RS76 units have been installed.
• Pedestrian access to the school remains fully maintained.
Brookfield Terrace
• A Hippo gully has been installed, and the chamber cover has been replaced.
• Tactile paving and the footpath have been installed.
2. Works lookahead:
Brookfield Terrace
• Drainage works and footpath upgrade works will continue as planned.
• Maintain safe pedestrian access throughout all phases of construction.
3. Early warning items:
Brookfield Terrace
• Drainage works and footpath upgrade works will continue as planned.
• Localised delays may occur during certain construction phases, but disruption is expected to remain minimal.
4. Other:
• The next update is on Friday, 05 June 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 15th May 2026:
1. Works elements completed / ongoing:
• Footpath and tree pit installation works are currently underway on Convent Road.
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
• Complete installation of RS76 units on Convent Road, followed by relocation of works to Brookfield Terrace.
• Works on Brookfield Terrace will be carried out between 08:00 and 18:00.
• Maintain safe pedestrian access throughout all phases of construction.
3. Early warning items:
• Works on Brookfield Terrace are scheduled to commence next week and will operate between 08:00 and 18:00.
• Localised delays may occur during certain construction phases, but disruption is expected to remain minimal.
4. Other:
• The next update is on Friday, 22 May 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 08th May 2026:
1. Works elements completed / ongoing:
• Footpath and tree pit installation works are currently underway on Convent Road.
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
• Continue footpath, kerbing works, drainage works and Tree Pits installation works on Convent Road.
• Maintain safe pedestrian access throughout all phases of construction.
3. Early warning items:
• Works on Convent Road will continue to operate under restricted working hours (10:00–16:00).
• Localised delays may occur during certain construction phases, but disruption is expected to remain minimal.
4. Other:
• The next update is on Friday, 15 May 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 01st May 2026:

1. Works elements completed / ongoing:
• Footpath and driveway installation works are currently underway on Convent Road.
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
• Continue footpath, kerbing works, drainage works and Tree Pits installation works on Convent Road.
• Implement the next phases of the Traffic Management Plan as required.
• Maintain safe pedestrian access throughout all phases of construction.
3. Early warning items:
• Works on Convent Road will continue to operate under restricted working hours (10:00–16:00).
• Localised delays may occur during certain construction phases, but disruption is expected to remain minimal.
4. Other:
• The next update is on Friday, 08 May 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 24th April 2026:
1. Works elements completed / ongoing:
• Footpath installation works are currently underway on Convent Road.
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
• Continue footpath, kerbing works and Tree Pits installation works on Convent Road.
• Implement the next phases of the Traffic Management Plan as required.
• Maintain safe pedestrian access throughout all phases of construction.
3. Early warning items:
• Works on Convent Road will continue to operate under restricted working hours (10:00–16:00).
• Localised delays may occur during certain construction phases, but disruption is expected to remain minimal.
4. Other:
• The next update is on Friday, 01 May 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 17th April 2026:
1. Works elements completed / ongoing:
• Footpath installation works are currently underway on Convent Road.
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
• Continue footpath, kerbing works and Tree Pits installation works on Convent Road.
• Implement the next phases of the Traffic Management Plan as required.
• Maintain safe pedestrian access throughout all phases of construction.
3. Early warning items:
• Works on Convent Road will continue to operate under restricted working hours (10:00–16:00).
• Localised delays may occur during certain construction phases, but disruption is expected to remain minimal.
4. Other:
• The next update is on Friday, 24 April 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 10th April 2026

1. Works elements completed / ongoing:
• Drainage works around the mini roundabout have been completed.
• Pavement works are currently underway at the entrance to Carysfort National School and are scheduled to be completed by Saturday, 11th April 2026.
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
• Continue footpath, kerbing works and Tree Pits installation works on Convent Road.
• Implement the next phases of the Traffic Management Plan as required.
• Maintain safe pedestrian access throughout all phases of construction.
3. Early warning items:
• Works on Convent Road will continue to operate under restricted working hours (10:00–16:00).
• Localised delays may occur during certain construction phases, but disruption is expected to remain minimal.
4. Other:
• The next update is on Friday, 17th April 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 03rd April 2026

1. Works elements completed / ongoing:
• Drainage works are completed.
• Footpath upgrades and tactile paving works are underway.
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
• Continue footpath and kerbing works around the roundabout, and then proceed to Convent Road, starting with the works at the Carysfort National School entrance.
• Implement the next phases of the Traffic Management Plan as required.
• Maintain safe pedestrian access throughout all phases of construction.
3. Early warning items:
• Works at the mini‑roundabout area will continue to operate under restricted working hours (10:00–16:00).
• Localised delays may occur during certain construction phases, but disruption is expected to remain minimal.
4. Other:
• The next update is on Friday, 10th April 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 27th March 2026

1. Works elements completed / ongoing:
• Drainage works are completed.
• Footpath upgrades and tactile paving works are underway.
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
• Continue footpath and kerbing works around the roundabout.
• Implement the next phases of the Traffic Management Plan as required.
• Maintain safe pedestrian access throughout all phases of construction.
3. Early warning items:
• Works at the mini‑roundabout area will continue to operate under restricted working hours (10:00–16:00).
• Localised delays may occur during certain construction phases, but disruption is expected to remain minimal.
4. Other:
• The next update is on Friday, 03rd April 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 20th March 2026

1. Works elements completed / ongoing:
• Drainage works are in progress.
• Footpath upgrades and tactile paving works are underway.
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
• Continue footpath, kerbing, and drainage works around the roundabout.
• Implement the next phases of the Traffic Management Plan as required.
• Maintain safe pedestrian access throughout all phases of construction.
3. Early warning items:
• Works at the mini‑roundabout area will continue to operate under restricted working hours (10:00–16:00).
• Localised delays may occur during certain construction phases, but disruption is expected to remain minimal.
4. Other:
• The next update is on Friday, 27 March 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 13th March 2026

1. Works elements completed / ongoing:
• Construction works at the mini‑roundabout have commenced.
• Footpath upgrades and tactile paving works are underway.
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
• Continue footpath, kerbing, and drainage works around the roundabout.
• Implement the next phases of the Traffic Management Plan as required.
• Maintain safe pedestrian access throughout all phases of construction.
3. Early warning items:
• Works at the mini‑roundabout area will continue to operate under restricted working hours (10:00–16:00).
• Localised delays may occur during certain construction phases, but disruption is expected to remain minimal.
4. Other:
• The next update is on Friday, 20 March 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news.
Friday, 17th July 2026:

1. Works elements completed / ongoing:
Upper Kilmacud Road
- All major works are complete, with landscaping works to be done during planting season
- Road is fully open with very minimal disruption.
- Snagging works to be carried out in the coming weeks.
2. Works lookahead:
Sandyford Road Car Park
- Height adjustment works to the bike shelter are still outstanding.
- Resin surfacing to existing levels is yet to be completed.
- Snag items, including reinstallation/correction of gullies.
Upper Kilmacud Road
- Snagging
3. Early warning items:
Sandyford Road Car Park
- Height adjustment works to the bike shelter are still outstanding.
- To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
Upper Kilmacud Road
- To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
- Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 03rd July 2026:
1. Works elements completed / ongoing:
Upper Kilmacud Road
- Road resurfacing works and line marking were completed.
- Only snagging is outstanding.
2. Works lookahead:
Sandyford Road Car Park
- Height adjustment works to the bike shelter are still outstanding.
- Resin surfacing to existing levels is yet to be completed.
- Snag items, including reinstallation/correction of gullies.
Upper Kilmacud Road
- Snags and clean-ups
3. Early warning items:
Sandyford Road Car Park
- Height adjustment works to the bike shelter are still outstanding.
- To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
Upper Kilmacud Road
- To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
- Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 19th June 2026:
1. Works elements completed / ongoing:
Upper Kilmacud Road
- • Concrete footpath, Landscaping works and concrete kerb poured for the footpath upgrade works were completed.
- Traffic sign installation work is ongoing.
2. Works lookahead:
Sandyford Road Car Park
- Height adjustment works to the bike shelter are still outstanding.
- Resin surfacing to existing levels is yet to be completed.
- Snag items including re-installation / correction of gullies.
Upper Kilmacud Road
- Snags and clean-ups
- Surfacing works
3. Early warning items:
Sandyford Road Car Park
- Height adjustment works to the bike shelter are still outstanding.
- To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times.
- Pedestrian access to the school will be maintained.
Upper Kilmacud Road
- A temporary Road closure of part of Upper Kilmacud Road, Dundrum, from Dundrum Garda Station to Dundrum College is proposed from Monday, 22nd June 2026 to Friday, 26th June 2026.
- To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 05th June 2026:
1. Works elements completed/ongoing:
Upper Kilmacud Road
• Concrete footpath and concrete kerb poured for the footpath upgrade works.
2. Works lookahead:
Sandyford Road Car Park
• Height adjustment works to the bike shelter are still outstanding.
• Resin surfacing to existing levels is yet to be completed.
• Snag items, including re-installation / correction of gullies.
Upper Kilmacud Road
• Landscape and planting works will continue as planned.
• Installation of one gully remains outstanding; however, this is currently under design review / being considered for omission.
3. Early warning items:
Sandyford Road Car Park
• Height adjustment works to the bike shelter are still outstanding.
• Resin surfacing to existing levels is yet to be completed.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
Upper Kilmacud Road
• Landscape and planting works will continue as planned.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 22nd May 2026:

1. Works elements completed / ongoing:
Upper Kilmacud Road
• A temporary ramp has been installed, and the manhole cover has been raised.
• Footpath upgrade works are currently underway.
2. Works lookahead:
Sandyford Road Car Park
• Height adjustment work on the bike shelter is still outstanding.
• Resin surfacing to existing levels is yet to be completed.
• Snag items, including re-installation / correction of gullies.
Upper Kilmacud Road
• Landscape works and footpath upgrade works will continue as planned.
• Installation of one gully remains outstanding; however, this is currently under design review / being considered for omission.
3. Early warning items:
Sandyford Road Car Park
• Height adjustment work on the bike shelter is still outstanding.
• Resin surfacing to existing levels is yet to be completed.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
Upper Kilmacud Road
• Landscape works and footpath upgrade works will continue as planned.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• The next update is on Friday, 29 May 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 15th May 2026:

1. Works elements completed / ongoing:
Sandyford Road Car Park
• Three bollards at the western entrance have been reinstalled.
• Line marking works have been completed.
Upper Kilmacud Road
• Drainage works have progressed, with new pipework now connected to the existing network.
• Footpath upgrade works are currently underway.
2. Works lookahead:
Sandyford Road Car Park
• Resin surfacing to existing levels is yet to be completed.
• Snag items, including re-installation / correction of gullies.
Upper Kilmacud Road
• Drainage works and footpath upgrade works will continue as planned.
• Installation of one gully remains outstanding; however, this is currently under design review / being considered for omission.
3. Early warning items:
Sandyford Road Car Park
• Resin surfacing to existing levels is yet to be completed.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
Upper Kilmacud Road
• Drainage works and footpath upgrade works will continue as planned.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• The next update is on Friday, 22 May 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 08th May 2026:
1. Works elements completed / ongoing:
Sandyford Road Car Park
• Bike shelters and stands at Dom Marmion Car Park have been installed.
Upper Kilmacud Road
• Drainage works, including gully and pipe connections, are ongoing.
• Footpath upgrade works are currently underway.
2. Works lookahead:
Sandyford Road Car Park
• Resin surfacing to existing levels is yet to be completed.
• Snag items, including re-installation / correction of gullies.
Upper Kilmacud Road
• Drainage works and footpath upgrade works will continue as planned.
3. Early warning items:
Sandyford Road Car Park
• Resin surfacing to existing levels is yet to be completed.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
Upper Kilmacud Road
• Drainage works and footpath upgrade works will continue as planned.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• The next update is on Friday, 15 May 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 01st May 2026:
1. Works elements completed / ongoing:
Sandyford Road Car Park
• Resurfacing works and line marking at Dom Marmion Car Park have been completed.
Upper Kilmacud Road
• Drainage works, including gully and pipe connections, are ongoing.
• Footpath upgrade works are currently underway.
2. Works lookahead:
Sandyford Road Car Park
• The bike shelter is scheduled to be installed on 05 May and 06 May.
• Snag items, including re-installation / correction of gullies.
Upper Kilmacud Road
• Drainage works and footpath upgrade works will continue as planned.
3. Early warning items:
Sandyford Road Car Park
• The bike shelter is scheduled to be installed on 05 May and 06 May.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
Upper Kilmacud Road
• Drainage works and footpath upgrade works will continue as planned.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• The next update is on Friday, 08 May 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 24th April 2026:
1. Works elements completed / ongoing:
Sandyford Road Car Park
• Resurfacing works and line marking at Dom Marmion Car Park have been completed.
Upper Kilmacud Road
• Drainage works, including gully and pipe connections, are ongoing.
• Footpath upgrade works are currently underway.
2. Works lookahead:
Sandyford Road Car Park
• The bike shelter is scheduled to be installed on 27 and 28 April.
Upper Kilmacud Road
• Drainage works and footpath upgrade works will continue as planned.
3. Early warning items:
Sandyford Road Car Park
• The bike shelter is scheduled to be installed on 27 and 28 April.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
Upper Kilmacud Road
• Drainage works and footpath upgrade works will continue as planned.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• The next update is on Friday, 01 May 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 17th April 2026:
1. Works elements completed / ongoing:
Sandyford Road Car Park
• Car park resurfacing works are scheduled to be carried out on Monday, 20th and Tuesday, 21st April.
Upper Kilmacud Road
• Drainage works, including gully and pipe connections, are ongoing.
• Footpath upgrade works are currently underway.
2. Works lookahead
Sandyford Road Car Park
• Car park resurfacing works are scheduled to be carried out on Monday, 20th and Tuesday, 21st April.
Upper Kilmacud Road
• Drainage works and footpath upgrade works will continue as planned.
3. Early warning items:
Sandyford Road Car Park
• Car park resurfacing works are scheduled to be carried out on Monday, 20th and Tuesday, 21st April.
• Temporary restrictions to car park use are expected during the works period.
Upper Kilmacud Road
• Drainage works and footpath upgrade works will continue as planned.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• The next update is on Friday, 24 April 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 10th April 2026

1. Works elements completed / ongoing:
• Bike shelter and bike stand installation works are ongoing.
• Installation of one gully has been completed and connected to the existing manhole.
2. Works lookahead:
Sandyford Road Car Park
• Continue bike shelter and bike stand installation works
• Continue rain garden installation works.
• Line marking works are scheduled to take place.
• Road pavement works are scheduled to take place.
• Maintain temporary traffic management and pedestrian access arrangements within the car park.
Upper Kilmacud Road
• Construction works are planned to commence next week at Upper Kilmacud Road.
• The works include upgrades to footpaths, tactile paving, drainage improvements, kerbing, and accessibility enhancements.
3. Early warning items:
Sandyford Road Car Park
• No significant early warning items at present.
• A small number of car park spaces will continue to remain temporarily unavailable during construction.
• Localised pedestrian diversions may be required as works progress.
• Construction works are planned to commence next week at Upper Kilmacud Road.
Upper Kilmacud Road
• Construction works are planned to commence next week at Upper Kilmacud Road.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• The next update is on Friday, 17th April 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 03rd April 2026

1. Works elements completed / ongoing:
• Bike shelter and bike stand installation works are ongoing.
• 1 catchpit manhole, 2 gullies and pipes and 2 gully gratings are installed and replaced.
2. Works lookahead:
• Continue bike shelter and bike stand installation works
• Continue rain garden installation works.
• Drainage works are scheduled to include the installation of 1 gully and the associated pipework.
• Line marking works are scheduled to take place.
• Road pavement works are scheduled to take place.
• Maintain temporary traffic management and pedestrian access arrangements within the car park.
3. Early warning items:
• No significant early warning items at present.
• A small number of car park spaces will continue to remain temporarily unavailable during construction.
• Localised pedestrian diversions may be required as works progress.
4. Other:
• The next update is on Friday, 10th April 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 27th March 2026
1. Works elements completed / ongoing:
• Bike shelter and bike stand installation works are ongoing.
• Nine pencil bollards were installed together with the RS76 units.
2. Works lookahead:
• Continue bike shelter and bike stand installation works.
• Continue rain garden installation works.
• Drainage works are scheduled to include the installation of 1 catchpit, 2 gullies, and the associated pipework.
• Line marking works are scheduled to take place.
• Maintain temporary traffic management and pedestrian access arrangements within the car park.
3. Early warning items:
• No significant early warning items at present.
• A small number of car park spaces will continue to remain temporarily unavailable during construction.
• Localised pedestrian diversions may be required as works progress.
4. Other:
• The next update is on Friday, 03rd April 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 20th March 2026

1. Works elements completed / ongoing:
• Bike shelter and bike stand installation works are ongoing.
• Rain garden installations are in progress.
2. Works lookahead:
• Continue bike shelter and bike stand installation works
• Continue rain garden installation works.
• Line marking works are scheduled to take place.
• Maintain temporary traffic management and pedestrian access arrangements within the car park.
3. Early warning items:
• No significant early warning items at present.
• A small number of car park spaces will continue to remain temporarily unavailable during construction.
• Localised pedestrian diversions may be required as works progress.
4. Other:
• The next update is on Friday, 27 March 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 13th March 2026

1. Works elements completed / ongoing:
• Drainage upgrades are ongoing within the Sandyford Road Car Park zone.
• Rain garden installations are in progress.
• Footpath works are underway.
• New street furniture installations are in progress.
• Pedestrian access is being maintained throughout the works area.
2. Works lookahead:
• Continue drainage installation and complete remaining rain garden works.
• Progress footpath finishing works.
• Continue installation of street furniture.
• Maintain temporary traffic management and pedestrian access arrangements within the car park.
3. Early warning items:
• No significant early warning items at present.
• A small number of car park spaces will continue to remain temporarily unavailable during construction.
• Localised pedestrian diversions may be required as works progress.
4. Other:
• The next update is on Friday, 20 March 2026.
• Weekly traffic updates: https://www.dlrcoco.ie/traffic-management/traffic-news
Friday, 15th May 2026:
1. Works elements completed / ongoing:
Monkstown Grove
• Footpath upgrade works have been completed.
• The car park area has been completed.
• Pedestrian access to the school remains fully maintained.
Oliver Plunkett Terrace
• Footpath upgrade works are ongoing.
• Mini Pillar, chambers, and ducts have been installed.
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
Monkstown Grove
• Construction works have progressed at Monkstown Grove.
• Outstanding works include carriageway resurfacing, line marking, and installation of road signs.
• No works are planned in the immediate term ahead of the surfacing works.
Oliver Plunkett Terrace
• Construction works are currently ongoing on Oliver Plunkett Terrace and will continue over the coming weeks.
• The works include upgrades to footpaths, tactile paving, kerbing, and accessibility enhancements.
3. Early warning items:
Monkstown Grove
• No works are planned in the immediate term ahead of the surfacing works.
Oliver Plunkett Terrace
• Construction works are currently ongoing on Monkstown Grove and will continue over the coming weeks.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• The next update is on Friday, 22 May 2026.
• For weekly traffic news updates, visit https://www.dlrcoco.ie/traffic-management/traffic-new
Friday, 08th May 2026:
1. Works elements completed / ongoing:
Monkstown Grove
• Footpath upgrade works are ongoing.
• The car park area has been completed.
• Pedestrian access to the school remains fully maintained.
Oliver Plunkett Terrace
• Footpath upgrade works are ongoing.
• Mini Pillar and a duct have been installed (SC02 NCR003 issued).
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
Monkstown Grove
• Construction works are currently ongoing on Monkstown Grove and will continue over the coming weeks.
• The works include upgrades to footpaths, tactile paving, drainage improvements, kerbing, and accessibility enhancements.
Oliver Plunkett Terrace
• Construction works are currently ongoing on Oliver Plunkett Terrace and will continue over the coming weeks.
• The works include upgrades to footpaths, tactile paving, kerbing, and accessibility enhancements.
3. Early warning items:
Monkstown Grove
• Construction works are currently ongoing on Monkstown Grove and will continue over the coming weeks.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
Oliver Plunkett Terrace
• Construction works are currently ongoing on Monkstown Grove and will continue over the coming weeks.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• The next update is on Friday, 15 May 2026.
• For weekly traffic news updates, visit https://www.dlrcoco.ie/traffic-management/traffic-new
Friday, 01st May 2026:
1. Works elements completed / ongoing:
Monkstown Grove
• Footpath upgrade works are ongoing.
• One gully has been installed.
• 2 no. sign poles have been installed.
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
Monkstown Grove
• Construction works are currently ongoing on Monkstown Grove and will continue over the coming weeks.
• The works include upgrades to footpaths, tactile paving, drainage improvements, kerbing, and accessibility enhancements.
3. Early warning items:
Monkstown Grove
• Construction works are currently ongoing on Monkstown Grove and will continue over the coming weeks.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• The next update is on Friday, 08 May 2026.
• For weekly traffic news updates, visit https://www.dlrcoco.ie/traffic-management/traffic-new
Friday, 24th April 2026:
1. Works elements completed / ongoing:
Monkstown Grove
• Footpath upgrade works are ongoing.
• Two gullies have been installed.
• 2 no. pencil bollards have been installed.
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
Monkstown Grove
• Construction works are currently ongoing on Monkstown Grove and will continue over the coming weeks.
• The works include upgrades to footpaths, tactile paving, drainage improvements, kerbing, and accessibility enhancements.
3. Early warning items:
Monkstown Grove
• Construction works are currently ongoing on Monkstown Grove and will continue over the coming weeks.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• The next update is on Friday, 01 May 2026.
• For weekly traffic news updates, visit https://www.dlrcoco.ie/traffic-management/traffic-new
Friday, 17th April 2026:
1. Works elements completed / ongoing:
• Footpath upgrade works are ongoing.
• 2 Tree pits have been installed.
• 13 no. Pencil bollards have been installed.
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
Dunedin Terrace
• Continue footpath upgrade works.
• Maintain safe pedestrian access throughout all phases of construction.
Monkstown Grove
• Construction works will commence on Monkstown Grove from next week.
• The works include upgrades to footpaths, tactile paving, drainage improvements, kerbing, and accessibility enhancements.
3. Early warning items:
Dunedin Terrace
• Localised delays may occur during certain construction phases, but disruption is expected to remain minimal.
Monkstown Grove
• Construction works are planned to commence next week at Monkstown Grove.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• The next update is on Friday, 24 April 2026.
• For weekly traffic news updates, visit https://www.dlrcoco.ie/traffic-management/traffic-new
Friday, 10th April 2026

1. Works elements completed / ongoing:
• Footpath upgrade works are ongoing.
• 2 Tree pits have been installed.
• 1 Gully has been installed and connected to the existing manhole.
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
Dunedin Terrace
• Continue footpath upgrade works.
• Maintain safe pedestrian access throughout all phases of construction.
Monkstown Grove
• Construction works will commence on Monkstown Grove from next week.
• The works include upgrades to footpaths, tactile paving, drainage improvements, kerbing, and accessibility enhancements.
3. Early warning items:
Dunedin Terrace
• Localised delays may occur during certain construction phases, but disruption is expected to remain minimal.
Monkstown Grove
• Construction works are planned to commence next week at Upper Kilmacud Road.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• The next update is on Friday, 17th April 2026.
• For weekly traffic news updates, visit https://www.dlrcoco.ie/traffic-management/traffic-new
Friday, 03rd April 2026

1. Works elements completed / ongoing:
• Public lighting ducting works are completed.
• Footpath upgrade works are ongoing.
• Tree pit installed.
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
• Continue footpath upgrade works.
• Maintain safe pedestrian access throughout all phases of construction.
3. Early warning items:
• Localised delays may occur during certain construction phases, but disruption is expected to remain minimal.
4. Other:
• The next update is on Friday, 10th April 2026.
• For weekly traffic news updates, visit https://www.dlrcoco.ie/traffic-management/traffic-new
Friday, 27th March 2026
1. Works elements completed / ongoing:
• Public lighting ducting works are ongoing.
• Footpath upgrade works are ongoing.
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
• Continue footpath upgrade works.
• Continue public lighting ducting works.
• Maintain safe pedestrian access throughout all phases of construction.
3. Early warning items:
• Localised delays may occur during certain construction phases, but disruption is expected to remain minimal.
4. Other:
• The next update is on Friday, 03 April 2026.
• For weekly traffic news updates, visit https://www.dlrcoco.ie/traffic-management/traffic-new
Friday, 17th July 2026:
1. Works elements completed / ongoing:
- Concrete reinstatement works and Tactile paving on Eden Lower and Eden Terrace Junction where completed.
- Handrails to park exit/access along Eden Road have been installed.
- Footpath parallel to park on Eden Road has been installed.
- Footpath upgrade works on Eden Road Lower and Harold Cres Junction have been completed.
- Pedestrian access to the school remains fully maintained.
- Traffic lights are switched off on the crossing in front of the school, with a temporary traffic light in place.
2. Works lookahead:
- Construction works will continue on Eden Road in the following weeks.
- The works include upgrades to footpaths, tactile paving, drainage improvements, kerbing, public lighting installation, tree pits and accessibility enhancements.
3. Early warning items:
- Construction works will continue on Eden Lower and Harold Cres Junction.
- During school holidays, work will be carried out between 08:00hrs and 18:00hrs.
4. Other:
- For weekly traffic news updates, visit https://www.dlrcoco.ie/traffic-management/traffic-new
Friday, 03rd July 2026:
1. Works elements completed / ongoing:
- Concrete reinstatement works and Tactile paving on Eden Lower and Eden Terrace Junction were completed.
- Footpath upgrade works on Eden Road Lower and Harold Cres Junction are completed.
- Footpath upgrades, Drainage works, and tree pit works on Harold Cres and Eden Road junction and along Eden Lower opposite the School are ongoing.
- Pedestrian access to the school remains fully maintained.
- Traffic lights are switched off on the crossing in front of the school, with a temporary traffic light in place.
2. Works lookahead:
- Construction works will continue at the junction of Harold Cres and Eden Road in the following weeks
- The works include upgrades to footpaths, tactile paving, drainage improvements, kerbing, public lighting installation, tree pits and accessibility enhancements.
3. Early warning items:
- Construction works will continue on Eden Lower and Harold Cres Junction.
- The Harold School has requested that works in front of the school be carried out after 30 June. A revised programme was prepared with the front of the school targeted to be done at the end of June.
- To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• For weekly traffic news updates, visit https://www.dlrcoco.ie/traffic-management/traffic-new
Friday, 19th June 2026:
1. Works elements completed / ongoing:
- Concrete reinstatement works and Tactile paving on Eden Lower and Eden Terrace Junction have been completed.
- Footpath upgrade works on Eden Road Lower and Harold Cres Junction are completed.
- Footpath upgrades, Drainage works, and tree pit works are ongoing on Harold Cres and Eden Road junction.
- Pedestrian access to the school remains fully maintained.
- Traffic lights are switched off on the crossing in front of the school, with a temporary traffic light in place.
2. Works lookahead:
- Construction works will continue on the junction of Harold Cres and Eden Road in the following weeks.
- The works include upgrades to footpaths, tactile paving, drainage improvements, kerbing, public lighting installation, tree pits and accessibility enhancements.
3. Early warning items:
- Construction works will continue on Eden Lower and Harold Cres Junction.
- The Harold School has requested that works in front of the school be carried out after 30 June. A revised programme was prepared with front of the school targeted to be done by the end of June.
- To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• For weekly traffic news updates, visit https://www.dlrcoco.ie/traffic-management/traffic-new
Friday, 05th June 2026:
1. Works elements completed / ongoing:
• Concrete reinstatement works and Tactile paving on Eden Lower and Eden Terrace Junction have been completed.
• Footpath upgrade works are ongoing on Eden Road Lower and Harold Cres Junction.
• Pedestrian access to the school remains fully maintained.
• Traffic lights are switched off on the crossing in front of the school, with a temporary traffic light in place.
2. Works lookahead:
• Construction works are currently ongoing on Eden Lower and Eden Terrace Junction and will continue over the coming weeks.
• The works include upgrades to footpaths, tactile paving, drainage improvements, kerbing, public lighting installation, and accessibility enhancements.
3. Early warning items:
• Construction works will continue on Eden Lower and Eden Terrace Junction.
• The Harold School has requested that works in front of the school be carried out after 30 June. A revised programme was prepared, with works in front of the school targeted for completion at the end of June.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• For weekly traffic news updates, visit https://www.dlrcoco.ie/traffic-management/traffic-new
Friday, 22nd May 2026:
1. Works elements completed / ongoing:
• Concrete reinstatement works for the public lighting ducts, chambers and mini pillars were completed this week.
• Mini pillars have been installed in the laneway.
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
• Construction works are currently ongoing on Eden Terrace and Eden Road Lower and will continue over the coming weeks.
• The works include upgrades to footpaths, tactile paving, drainage improvements, kerbing, public lighting installation, and accessibility enhancements.
3. Early warning items:
• Construction works will continue on Eden Terrace and Eden Road Lower.
• The Harold School has requested that works in front of the school be carried out after 30 June. A revised programme is currently being prepared.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• The next update is on Friday, 29 May 2026.
• For weekly traffic news updates, visit https://www.dlrcoco.ie/traffic-management/traffic-new
Friday, 15th May 2026:
1. Works elements completed / ongoing:
• Public lighting ducts, chambers and mini pillars have been installed.
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
• Construction works are currently ongoing on Eden Terrace and Eden Road Lower and will continue over the coming weeks.
• The works include upgrades to footpaths, tactile paving, drainage improvements, kerbing, public lighting installation, and accessibility enhancements.
3. Early warning items:
• Construction works will continue on Eden Terrace and Eden Road Lower.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• The next update is on Friday, 22 May 2026.
• For weekly traffic news updates, visit https://www.dlrcoco.ie/traffic-management/traffic-new
Friday, 08th May 2026:
1. Works elements completed / ongoing:
• Two mini pillars, associated ducting, and the public lighting pole foundation have been completed.
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
• Construction works are currently ongoing on Eden Road Lower and will continue over the coming weeks.
• The works include upgrades to footpaths, tactile paving, drainage improvements, kerbing, public lighting installation, and accessibility enhancements.
3. Early warning items:
• Construction works will continue on Eden Road Lower.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• The next update is on Friday, 15 May 2026.
• For weekly traffic news updates, visit https://www.dlrcoco.ie/traffic-management/traffic-new
Friday, 01st May 2026:
1. Works elements completed / ongoing:
• One public lighting chamber, associated ducting, and the public lighting pole foundation have been completed.
• Tactile paving and the concrete footpath have been installed.
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
• Construction works are currently ongoing on Eden Road Lower and will continue over the coming weeks.
• The works include upgrades to footpaths, tactile paving, drainage improvements, kerbing, public lighting installation, and accessibility enhancements.
3. Early warning items:
• Construction works will continue on Eden Road Lower.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• The next update is on Friday, 08 May 2026.
• For weekly traffic news updates, visit https://www.dlrcoco.ie/traffic-management/traffic-new
Friday, 24th April 2026:
1. Works elements completed / ongoing:
• Temporary signals have been installed on plinths for traffic signal works.
• Pedestrian access to the school remains fully maintained.
2. Works lookahead:
• Construction works will commence on Eden Road Lower from next week.
• The works include upgrades to footpaths, tactile paving, drainage improvements, kerbing, and accessibility enhancements.
3. Early warning items:
• Construction works will commence on Eden Road Lower from next week.
• To minimise disruption, all traffic‑impacting works will take place between 10:00 and 16:00, avoiding busy school and commuter peak times. Pedestrian access to the school will be maintained.
4. Other:
• The next update is on Friday, 01 May 2026.
• For weekly traffic news updates, visit https://www.dlrcoco.ie/traffic-management/traffic-new
- St. Patrick's Girls School and Boys National School, Hollypark
- St. Kevin's National School, Sallynoggin
Project Overview
Dún Laoghaire-Rathdown County Council is working with the National Transport Authority (NTA) to deliver their “Safe Routes to School” (SRTS) Programme, the aim of which is to improve safety at school entrances, improve access routes to schools and encourage as many pupils as possible in primary and post-primary schools to walk and cycle.

The SRTS Programme includes the delivery of “School Zones” consisting of public realm upgrades outside schools, which will:
- Reduce vehicular congestion at school gates.
- Encourage drivers to slow down in the vicinity of a school.
- Reduce vehicle drop-offs, pick-ups and vehicles idling at school gates.
- Highlight the presence of schools and their vulnerable road users.
- Provide the public with cleaner air, safer streets, and more vibrant and inclusive public spaces.
The proposed interventions at each school are based on survey findings, audits, and consultations with the schools, developed by SRTS An Taisce's Infrastructure Officer in collaboration with the Local Authority and the National Transport Authority (NTA).
A list of schools in DLR is shown in the table below:
