April 2025:
Love Our Laneways Launch:
September 2024:

1. Work Elements Completed / On-Going
- Road line markings completed
- Toddler play element installed. Safety surfacing to follow.
- Site furniture installed
- Boulders installed and located within rain gardens
- Surfacing & kerbing completed
2. Upcoming Work – 4-week look-ahead
- Snagging of concrete kerbing, macadam finishes, and site furniture
- Safety surfacing for the toddler play element to be poured
- Sallynoggin Gateway structure foundations to be poured
- Gateway structure to be delivered to the site & installed
- Artwork on the laneway surface to commence
3. Early Warning Items
- The laneway between Pearse Gardens & Pearse Park will be partially closed to facilitate artwork taking place.
- The Welfare unit is to be located outside Sallynoggin College of Further Education
About

DLR, in collaboration with A Playful City* and the local community are developing a co-created vision for Pearse Drive laneway in Sallynoggin to enhance it as a more playful, people-centred place for the community, by the community.
Pearse Drive, Sallynoggin, is defined by a series of long streets running between Sallyglen Road and Rochestown Avenue, with the majority of retail to the northeast of the laneway and public amenities to the south. With close proximity to places such as St Josephs' Boys AFC and the Community & Senior Centre, it has the potential to become a key link between these key stakeholders, as well as an inclusive, accessible and attractive place for the local community.
This exciting and innovative project will consist of multiple phases, from community visioning to design and execution, with each phase involving listening to and collaborating with community members, as well as LADT and Sallnoggin College of Further Education.
The project report is available to read below. Click to expand and see the report.