Samuel Beckett Civic Campus Phase 2

Status: Phase 2 Project 2a - Ballyogan Library including fit out - Construction
Phase 2 Project 2b - Sports Campus including swimming pool - Design

Dún Laoghaire-Rathdown County Council has been awarded a €5m grant under the Large Scale Sport Infrastructure Fund scheme. This funding will be used for Phase 2 of the Samuel Beckett Civic Campus. This phase will include:

  • A multi-purpose sports building including sports hall, children's and 25m swimming pools, dance studio, and a gym
  • A two-storey library
  • A two-storey car park
  • A hard landscaped Civic Plaza

 

Ballyogan Library including fit out. Work commenced on site on the 14th August and demolitions / strip-outs are underway. It is expected that the library fit-out will be completed in March/April 2024.