Stillorgan Park Road – from N11 to Carysfort Avenue, Blackrock
Junction buildouts, new kerbing, drainage, traffic signal ducting and all associated works to construct pedestrian and cyclist improvement schemes will continue until December 2024 between 08:00 and 18:00 hours.
Project Updates
November Updates: (See Gallery at bottom of page for Images)
- Works Elements completed / ongoing
- N11 night works complete. Central Traffic island works and new signal poles installed and in place.
- Planting at N11 junction and Patrician villas junction.
- Carriageway resurfacing is underway from Roundabout to N11. Ramps are underway at the roundabout section.
- Works to continue on Patrician Villas junction.
- Works to continue on Stillorgan Park Ave junction.
- Red cycle track surfacing ais lmost complete throughout the scheme.
- Landscaping works throughout the scheme.
- Works lookahead / Four Week Look Ahead:
- Roundabout ramp installation and ramp installation at Patrician Villas, Stillorgan Park Ave, and Stillorgan Grove junction are underway. A Stop-Go system and Traffic Management Plan will be in place.
- Additional Trees and landscaping works to continue.
- Line marking
- Early Warning items
- Stop-Go in place over the next 4 weeks for road and cycle track resurfacing, line marking and ramp installation at Stillorgan Park Avenue, Patrician Villas and Stillorgan Grove.
- Works on Ramp installation and resurfacing to take place over the next 4 weeks with a Stop / Go system Traffic Management Plan in place.
- During the works, it was identified that the root zone of a number of trees was impacted by the new layout. Two opinions from Arboricultural experts were sought with the recommendation that 11 trees are to be removed. See the image in the Gallery for the identified trees. As a mitigation measure, we are proposing the following replanting schedule: 18 TILIA HENRYANA (Lime Trees). This is in addition to the 30 trees already proposed as part of the scheme.
October Updates: (See Gallery at bottom of page for Images)
- Works Elements completed / ongoing
- N11 night works underway. Central Traffic island works and new signal poles. A Stop-Go system and Traffic Management Plan will be in place.
- Carriageway resurfacing is underway from Roundabout to N11. Ramps are to be installed at the roundabout.
- Landscaping works throughout the scheme.
- Works lookahead / Four Week Look Ahead:
- N11 night works to commence the week of the 21st of October 2024.
- Roundabout ramp installation construction is underway. A Stop-Go system and Traffic Management Plan will be in place.
- Works to continue on Patrician Villas junction.
- Works to continue on Stillorgan Park Ave junction.
- Works to continue on N11 junction. Nightworks will take place on the N11 / Stillorgan Park Road junction.
- Additional Trees and landscaping works to continue
- Line marking
- Early Warning items
- Stop-Go is in place over the next 4 weeks for road and cycle track resurfacing, and ramp installation at Stillorgan Park Avenue, Patrician Villas and Stillorgan Grove.
- Works on Ramp installation and resurfacing to take place over the next 4 weeks with a Stop / Go system Traffic Management Plan in place.
September Updates: (See Gallery at bottom of page for Images)
- Works Elements completed / ongoing
- Stillorgan Park Road central island median works are ongoing.
- Roundabout resurfacing and construction are underway. A Stop-Go system and Traffic Management Plan will be in place.
- Red cycle track surfacing was completed on the north and south sides from Carysfort to Meadow Court.
- Carriageway resurfacing completed from Carysfort to Meadow Court. Ramps installed at side road junctions. Road Marking complete to Coppinger glade.
- Works are underway on Patrician Villas junction.
- Works to be underway on Stillorgan Park Ave.
- Works lookahead / Four Week Look Ahead:
- Roundabout resurfacing and construction are underway. A Stop-Go system and Traffic Management Plan will be in place.
- Works to continue on N11 junction. Nightworks will take place on the N11 / Stillorgan Park Road junction in mid-October. A Stop / Go system and Traffic Management Plan will be in place.
- Landscaping works will commence in October
- Early Warning items
- Stop-Go is in place over the next 2 weeks for road and cycle track resurfacing, concrete footpath pours and utility road crossings.
- Works on the roundabout to take place over the next 2.5 weeks with a Stop-Go system, Temporary traffic lights and a Traffic Management Plan in place.
August Updates:
- Works Elements completed / ongoing
- N11 works underway. Public lighting and ducting road crossing complete.
- Roundabout resurfacing and construction underway. A Stop / Go system and Traffic Management Plan will be in place.
- Installation of ducting , drainage, kerbing and concrete footpath from the roundabout to Stillorgan Park Avenue underway.
- Red cycle track surfacing completed on north and south side from Carysfort to Meadow Court.
- Carriageway resurfacing completed from Carysfort to Meadow Court . Ramps installed at side road junctions. Road Marking complete to Coppinger glade.
- Works lookahead / Four Week Look Ahead:
- Roundabout resurfacing and construction underway. A Stop / Go system and Traffic Management Plan will be in place.
- Works to commence on Patrician Villas junction.
- Works to commence on Stillorgan Park Ave.
- Works to continue on N11 junction. Nightworks will take place on the N11 / Stillorgan Park Road junction in mid September. A Stop / Go system and Traffic Management Plan will be in place.
- Early Warning items
- Stop Go in place over the next 2 weeks for road and cycle track resurfacing , concrete footpath pours and utility road crossings.
- Works on Roundabout to take place over the next 2.5 weeks with a A Stop / Go system , Temporary traffic lights and Traffic Management Plan in place.
1. Works Elements completed / ongoing
- Ducting, Drainage, concrete footpaths and tactile paving were completed on the south side from Carysfort Avenue to Stillorgan Grove
- Toucan crossing traffic poles installed near Coppinger Glade and Coppinger Wood
- 4 Bus stop benches installed
- 3 bus stops complete
- Red cycle track surfacing was completed on the south side on either side of Coppinger Glade and Obelisk Avenue
- Carriageway resurfacing completed from Carysfort to Meadow Court. Ramps installed at side road junctions.
2. Works lookahead / Four Week Look Ahead:
- Road markings are to commence next week.
- Cycle track Red surfacing to be completed from Carysfort to Meadow Court on both sides of the road 2 weeks from now
- Installation of ducting, drainage, kerbing and concrete footpath from the roundabout to Stillorgan Park Avenue (south side)
- Installation of ducting, drainage, kerbing and concrete footpath from the roundabout to Stillorgan Grove (south side)
- Works to commence on Patrician Villas junction.
- Works to commence on Stillorgan Park Ave.
- Works to commence on N11 junction. Nightworks will take place on the N11 / Stillorgan Park Road junction next Wednesday and Thursday 7th and 8th of August 2024 until 5.30 am. A Stop / Go system and Traffic Management Plan will be in place.
3. Early Warning items
- Stop-Go is in place over the next 2 weeks for road and cycle track resurfacing, concrete footpath pours and utility road crossings.
- Works on Stillorgan Park Road / N11 will commence next week with night works.
July Updates:
1. Works Elements completed / ongoing
- Ducting, Drainage , concrete footpaths and tactile paving were completed on the south side from Carysfort Avenue to Stillorgan Grove
- A toucan crossing civils works completed near Coppinger Glade and Coppinger Wood
- 3 Bus stop benches installed
- 3 bus stops complete
2. Works lookahead / Four Week Look Ahead:
- Carriageway resurfacing is underway from Carysfort to Coppinger Glade. Resurfacing to be complete as far as Meadow Court 2 weeks from now.
- Cycle track Red surfacing to be completed from Carysfort to Meadow Court on both sides of the road
- Installation of ducting, drainage, kerbing and concrete footpath from the roundabout to Stillorgan Park Avenue (south side)
- Installation of ducting, drainage, kerbing and concrete footpath from the roundabout to Stillorgan Grove (south side)
3. Early Warning items
- Stop-Go is in place over the next 2 weeks for road resurfacing and concrete footpath pours
- Works on Stillorgan Park Road / N11 are due to start early to mid-August
June Updates:
1. Works Completed:
- Pavement works
- Pavement preparation
- Slipform kerbing
- Concrete Works
2. Works Lookahead / Four Week Look Ahead:
- South Side – Complete Ducting install & Gas Transmission Main Protection Slab
- South Side- Kerbing & Footpath Install
- South Side – Cycleway Surfacing
- North Side – Cycleway Surfacing
May Updates:
1. Works Completed:
- Bus Stop works
- Pavement Preparation
- Crossing Install
2. Works Lookahead / Four Week Look Ahead
- Complete Site Clearance Works (South Side)
- Complete Ducting Installation (South Side)
- Complete Concrete Footpath Installation (South Side)
- Complete Road Crossings
- Site Clearance North Side
- Footpath Installation North Side
- Ducting/ Service Installation North Side
- Concrete Footpath Installation North Side
April Updates:
1. Works Completed:
- Concrete Pavement Installation
- Pedestrian Crossing
- Site clearance
- Bus Stop
2. Works Lookahead / Four Week Look Ahead:
- Complete Site Clearance Works (South Side)
- Complete Ducting Installation (South Side)
- Complete Concrete Footpath Installation (South Side)
- Complete Road Crossings
- Set up TM on the North side
- Site Clearance North Side
- Footpath Installation North Side
- Ducting/ Service Installation North Side
- Concrete Footpath Installation North Side
March Updates:
1. Works Completed:
- Spare Ducting & Lighting Ducting Installation, new chambers
- Concrete Pavement Installation
- 200m footpath complete
- Ducting, drainage, surface course etc.
2. Works Lookahead / Four Week Look Ahead:
- Complete Site Clearance Works (South Side)
- Complete Ducting Installation (South Side)
- Complete Concrete Footpath Installation (South Side)
- Complete Road Crossings
- Set up TM on the North side & Commence site clearance works in this area.