Ongoing Schemes
Enniskerry Road, Dublin 18
This project is being delivered between the Housing Agency, Respond and Tuath Housing Associations, the Housing Finance Agency and us. Works have been completed in respect of Phase 1, delivering 50 new cost-rental homes and 27 new homes for social housing. Phase 2 is scheduled for completion in Q2 2022 which will deliver a further 78 new homes.
Rockville Green, Glenamuck
Part 8 planning permission was granted on the 7th of June 2019 for the construction of 13 new homes for social housing. Construction of this scheme commenced in April 2021.
Ballyogan Square, Ballyogan
Part 8 planning permission was granted on the 7th of June 2019 for the construction of 119 homes. Construction on this project is scheduled to commence shortly with completion due in Q2 2023.
Loughlinstown Wood, Loughlinstown
42 new homes are planned to be developed on a site provided by us and will be delivered between Co-Operative Housing Ireland, Loughlinstown Co-Op, the Housing Finance Agency and Dún Laoghaire-Rathdown County Council.
Shanganagh Residential Lands
The proposed development seeks the construction of:
• 597 homes,
• a crèche facility,
• a local shop and cafe,
• several resident services and amenities.
The development site is located between Shanganagh Castle to the east, the Dublin Road to the west, Castle Farm to the north and Shanganagh Park to the south, in the townlands of Shanganagh, Cork Little and Shankill, Co. Dublin.
We, in partnership with the Land Development Agency (LDA), received confirmation of full planning permission for this development in July 2020. Tenders have been received and are currently under review. Construction is scheduled to commence in 2022 with the first homes will be completed in 2024.
Completed Schemes
Broadford Court, Ballinteer
Designed for our senior citizens, this project will provide 21 new one-bed homes as well as a community room and a plant room. Construction started in August 2017 and completed in November 2021.
Ballyogan Avenue, Ballyogan
This project is the redevelopment of the former local resource centre into 2 two-bed apartments to be used for social housing. Construction started in February 2020 and this scheme was completed in March 2021.
Abbeyview House, Monkstown
This project of 11 new homes for social housing was delivered on a site provided by us between Clúid Housing Association, the Housing Finance Agency and us. This scheme was completed in November 2020.
Fitzgerald Park, Mounttown
50 homes consisting of a mixture of 1, 2, 3 & 4 bed houses and apartments were completed in phases between December 2018 and throughout 2019. All homes have been allocated.
Rosemount Court, Dúndrum
44 homes consisting of a mixture of 1, 2, 3 & 4 bed houses and apartments were completed on 5th December 2018. New tenants commenced moving in on the same day.
Rochestown Gardens (Phase 3), Sallynoggin
14 homes consisting of 12 x one-bed and 2 x two-bed homes were completed on the 19th October 2018. This is the final stage of the refurbishment and redevelopment at Rochestown House. New tenants commenced moving in on the 23rd October 2018.
Pottery Road, Glenageary
4 x one-bed homes were completed on the 10th August 2018. The tenants commenced moving in on 13th August 2018.
The Brambles, Sallynoggin
10 x one-bed homes were completed on 11th June 2018. New tenants commenced moving in on 18th June 2018. Six of the homes are fully accessible and all homes have a level access shower.
George’s Place, Dún Laoghaire
12 homes consisting of 12 x 2-bed 2 storey homes were completed on 6th June 2018. Tenants commenced moving in on 11th June 2018.
Temple Road, Blackrock
3 homes consisting of 2 x 2-bed duplex home and 1 x 3-bed ground floor fully accessible home were completed on 1st June 2018. Tenants commenced moving in on 6th June 2018.
The Mews, Sallynoggin
4 x one-bed homes over 2 storeys were completed on Friday 8th December 2017. New tenants commenced moving in on Monday 11th December 2017.
St Michael’s Terrace, Dún Laoghaire
4 homes consisting of 3 x one-bed and 1 x four-bed homes were completed on the 6th of September 2017. New tenants commenced moving in on the 12th September 2017.