Notice is hereby given that Dún Laoghaire Rathdown County Council, in exercise of the powers under Section 10 of the Road Traffic Act, 2004, in the interests of road safety and to facilitate the resurfacing of the M50 motorway, has made an Order entitled

Road Works Speed Limit Order, No.1 of 2019 on the M50 motorway in the County of Dún Laoghaire Rathdown to apply a road works speed limit as follows:

M50 Southbound will run from 09/09/2019 until 11/10/2019 or for the duration of the works whichever is the earlier.

Description of speed limit order 80km/hr:

  • Part of the Southbound M50 between a point 120 metres South of the existing R117 overbridge to a point 620 metres South of the R117 overbridge

(Total 500m in length).

  • Part of the Southbound M50 diverge at Junction 14 from the start of the diverge taper to a point on the diverge ramp 420 metres West of the yield line of the diverge off-ramp at Junction 14

(Total 485m in length).

Description of speed limit order 60km/hr:

  • Part of the Southbound M50 between a point 620 metres South of the existing R117 Overbridge to a point 120 metres South of the M11 Overbridge (M50 Junction 17/M11 J4)

(Total 8,000m in length).

  • Part of the Southbound M50 merge at Junction 13 from a point 50 metres East of the start of the merge on-ramp at M50 Junction 13 to the end of the merge taper

(Total 1250m in length).

 

  • Part of the Southbound M50 diverge at Junction 15 from the start of the diverge taper to a point on the diverge ramp 40 metres West of the stop line of the diverge off-ramp at Junction 15

(Total 555m in length).

  • Part of the Southbound M50 merge at Junction 15 from a point 75 metres South of the start of the merge on-ramp at M50 Junction 15 to the end of the merge taper

(Total 480m in length).

  • Part of the Southbound M50 diverge at Junction 16 from the start of the diverge taper to a point on the diverge ramp 60 metres West of the stop line of the diverge off-ramp at Junction 16

(Total 525m in length).

  • Part of the Southbound M50 merge at Junction 16 from a point 65 metres South of the start of the merge on-ramp at M50 Junction 16 to the end of the merge taper

(Total 575m in length).

M50 Northbound will run from 23/09/2019 until 08/11/2019 or for the duration of the works whichever is the earlier.

Description of speed limit order 80km/hr:

  • Part of the Northbound M50 between a point 335 metres South of the existing Crinken Lane overbridge to a point 165 metres North of the Crinken Lane overbridge

(Total 500m in length).

Description of speed limit order 60km/hr:

  • Part of the Northbound M50 between a point 165 metres North of the existing Crinken Lane overbridge to a point 300 metres West of the R113 overbridge

(Total 8000m in length).

  • Part of the Northbound M50 diverge at Junction 17 (M11 Junction 4) from the start of the diverge taper to a point on the diverge ramp 70 metres North of the Lordello Road overbridge

(Total 450m in length).

  • Part of the Northbound M50 diverge at Junction 16 from the start of the diverge taper to a point on the diverge ramp 55 metres East of the stop line of the diverge off-ramp at Junction 16

(Total 605m in length).

  • Part of the Northbound M50 merge at Junction 16 from a point 80 metres West of the start of the merge on-ramp at M50 Junction 16 to the end of the merge taper

(Total 700m in length).

  • Part of the Northbound M50 diverge at Junction 15 from the start of the diverge taper to a point on the diverge ramp 130 metres East of the stop line of the diverge off-ramp at Junction 15

(Total 500m in length).

  • Part of the Northbound M50 merge at Junction 15 from a point 35 metres North of the start of the merge on-ramp at M50 Junction 15 to the end of the merge taper

(Total 590m in length).

 

  • Part of the Northbound M50 diverge at Junction 13 from the start of the diverge taper to a point on the diverge ramp 420 metres East of the stop line of the diverge off-ramp at Junction 13

(Total 480m in length).

 