Road improvement scheme - including sections of Sandyford, Enniskerry and Hillcrest Roads at Lamb's Cross

 

Status:  At detailed design.

 Part 8 Planning approved June 2016.  CPO (Compulsory Purchase Order) Blackglen Road Improvement Scheme (Phase 1 of the Blackglen Road/Harold's Grange Road Improvement Scheme) was published on 19th April 2018.  The CPO was confirmed on 13th February 2019.

 

A Part 8 planning scheme was approved for the Blackglen Road / Harold’s Grange Road Improvement Scheme (Sandyford / Ballinteer) in November 2007.  Due to the economic downturn, the scheme was put on hold.  A revised Part 8 was approved by the Council in June 2016.  A detailed design is underway.  CPO (Compulsory Purchase Order) was published on 19th April 2018 and confirmed on 13th February 2019.  The 3km scheme will be constructed on a phased basis as funding becomes available.

The current project (Blackglen Road Improvement Scheme) does not include improvement works to the Harold's Grange Road.

 